Archives for posts tagged ‘Framing’

4230 Raleigh Street Construction Update – Framing is underway

We are finally coming out of the ground with 4230 Raleigh Street. Framing has come along quickly and should be finished up later this week.
Lumber is on site and the crew are getting started.

The steel beam is in place and the basement slab is cured.

Below is a close up showing the brick ledge as well [...]

4230 Raleigh Street Construction Update – Foundations are Complete

It’s been a few weeks since we’ve updated the blog regarding our construction progress. The combination of a two week delay as we waited for Xcel Energy to hook up power to the site and some adverse weather conditions put a damper on visible progress. We are now well on our way and figured we [...]